Soilworks products are the industry’s top standard due to our insistence on creating high performance soil stabilization and dust control products that stand up to rigorous testing – both in the lab and in the field. Our commitment to quality and performance has led to our involvement and testing in hundreds of real-world situations. The following library of reports, presentations, specifications, approvals and other similar documents provide you, our customer, the transparency and dependable assurance that is expected from Soilworks.

Daily Construction Report Fort Ord Clean Up (TPD0807027)

Appendix C – Contractor Daily Report

Daily Construction Reports Summary of Issues and Resolutions

Date

Issue

Resolution

Page

01/15/08

Elevated spikes in PDR dust monitor readings occurred from 9:15 to 11am when the fog rolled in.

Fog caused erroneous readings in PDRs. Presence of fog will be recorded in daily reports and checked against PDR dust monitor readings.

17

01/15/08

A Weston Equipment Operator operating a D6R bulldozer backed into and grazed a communications service pole at approximately 8:40am. The pole was broken off at the base causing the pole to relocate 2-3 feet. There was no damage to the communication lines.

Weston Site Supervisor (Charlie Smith) notified Mark Edwards (LFR) and Bruce More (Weston SUXOS). The utility pole is scheduled to be removed and relocated, therefore, permanent repair was not required. Ahtna installed a pole 8 feet into the ground immediately next to the broken pole, then bolted the two poles together to act as a brace. To prevent from occurring again, Weston will maintain a minimum 5- ft radius around utility poles.

18

01/17/08

The PDR on the west side fell on the ground likely causing instantaneous elevated readings

Additional support will be added to the PDR stand to prevent a re-occurrence. Event recorded in daily reports and checked against PDR dust monitor readings

21

01/18/08

The PDR on the west side fell on the ground likely causing instantaneous elevated readings

Additional support was added to the PDR stand. Event recorded in daily reports and checked against PDR dust monitor readings.

23

02/04/08

Erosion was noted along a step slope adjacent to General Jim Moore Blvd.

Weston personnel installed approximately 250 linear feet of straw wattle along the southern edge of the scraped road on General Jim Moore Blvd to minimize erosion along this steep slope.

40

02/04/08

Potential erosion issue to the NRMA identified along the eastern side of the sift plant operations.

Weston personnel installed 1,000 linear feet of silt fence along the eastern edge of the screening staging area at approximately 35 feet east of the NRMA boundary line.

Contact RPM to devise plan to address dust issues moving forward.

42

02/11/08

PDR Location 2 data lost during transfer from PDR to laptop.

49

02/14/08

Wind blowing dust in direction of homes.

Work activities were immediately shut down to minimize dust transport off-site (Transport of MRS.SEA.1 scraped soil was not completed as a result).

56

Date

Issue

Resolution

Page

02/27/08

Elevated PDR dust monitor ratings occurred in the afternoon when the fog came in.

Fog caused erroneous readings in PDRs. Presence of fog is recorded in daily reports and checked against PDR dust monitor readings.

73

03/06/08

The PDR south of A-66 fell on the ground/dirt causing elevated readings.

Additional support was added to the PDR stand. Event recorded in daily reports and checked against PDR dust monitor readings

85

03/20/08

Location 1 PDR data lost due to operator error.

105

03/25/08

Considerable cultural debris contacts encountered during geophysical investigations in SCA-53.

Weston personnel began scraping SCA-53 in 2-3 foot lifts due to the presence of significant asphalt and concrete.

112

03/26/08

Considerable cultural debris contacts encountered during geophysical investigations in multiple SCAs.

Weston scraped SCAs 25, 31, 32, 40, 42, and 43 to depths greater than 6 inches in depth to remove detectable contacts.

Weston continued scraping SCAs A-53, 56, and 41

114

03/31/08

Considerable cultural debris contacts encountered during geophysical investigations in multiple SCAs.

Weston continued scraping SCA A-53 using the excavator. There was significant amount of asphalt at this SCA. Weston personnel scraped SCA A-32, 33, and 35 to depths greater than 6 inches with the support of UXO personnel

120

04/02/08

Considerable cultural debris contacts encountered during geophysical investigations in SCA 32.

Weston personnel scraped SCA 32 to depths greater than 6 inches with the support of UXO personnel

124

04/02/08

Considerable cultural debris contacts encountered during geophysical investigations in SCA 26.

Weston scraped SCA 26 to depths greater than 6 inches with the support of UXO personnel

124

04/03/08

Considerable cultural debris contacts encountered during geophysical investigations in multiple SCAs.

Weston scraped SCA 32, 36, 37 and 38 to depths greater than 6 inches with the support of UXO personnel

126

04/03/08

Considerable cultural debris contacts encountered during geophysical investigations in multiple SCAs.

Weston scraped SCAs 66 and 70, and latrines 5 and 6, to depths greater than 6 inches with the support of UXO personnel

126

04/04/08

Location 2 PDR fell on the ground causing the elevated dust reading (max instantaneous reading = 13.818 mg/m3)

Additional support was added to the PDR stand. Event recorded in daily reports and checked against PDR dust monitor readings.

127

Date

Issue

Resolution

Page

04/07/08

Location 2 PDR fell on the ground causing the elevated dust reading

Additional support was added to the PDR stand. Event recorded in daily reports and checked against PDR dust monitor readings.

129

04/14/08

Location 2 and 3 PDRs fell on the ground causing the elevated dust reading

Additional support was added to the PDR stand. Event recorded in daily reports and checked against PDR dust monitor readings.

139

05/21/08

Dust emissions.

Weston mobilized subcontractor Superior Hydroseeding to begin applying a soil stabilization product (Gorilla-Snot) across the cleared and grubbed roadway area in Seaside MRS 2, which did not have SCA point or polygons.

194

06/12/08

No PDR data due to operator error – data was not recorded or downloaded.

225

07/09/08

PDR at Location 2 was in close vicinity of mowing operations, leading to high readings

Vegetation debris caused erroneous readings in PDR. Event was recorded in daily reports and checked against PDR dust monitor readings.

263

07/14/08

Considerable cultural debris contacts encountered during geophysical investigations in SCA 160.

The construction crew conducted additional scraping of SCA polygon W160 today to remove anomalies detected by DGM instruments.

274