Reference Library

Soilworks products are the industry’s top standard due to our insistence on creating high performance soil stabilization and dust control products that stand up to rigorous testing – both in the lab and in the field. Our commitment to quality and performance has led to our involvement and testing in hundreds of real-world situations. The following library of reports, presentations, specifications, approvals and other similar documents provide you, our customer, the transparency and dependable assurance that is expected from Soilworks.

Evaluating BMPs for Temporary Stockpiling of Poultry Litter (TPD0812031)

Executive Summary

 

Most poultry farms lack adequate on-farm capacity to store total cleanout litter in their manure storage sheds. As a result, storing poultry litter in the field after removal from the poultry production facility prior to spreading as a fertilizer during the production of crops is a common practice in the Delmarva region. There is a lack of research, however, on the potential losses of nutrients during this period of field storage. The objectives of this project were to quantify the types and amounts of nutrients being lost from these piles during storage and to evaluate techniques that can be used to minimize these nutrient losses. Production-size piles were utilized for this project, because all previous research used small research-size piles that may not adequately compare to actual practices used in production agriculture. Two methods were used to monitor nutrient losses from poultry litter piles. One method used runoff pans to collect runoff/leachate from the edges of poultry litter piles. With this method, a total of six replications of runoff/leachate were collected from three different piles during a three-year period. Assuming a pile size of 100 tons of poultry litter, the results showed that the average amounts of inorganic N, total P, potassium, and sulfur in the runoff/leachate were 17, 3, 113, and 32 pounds, respectively. The other method of measuring nutrient losses from poultry litter piles involved taking soil samples from either the surface 36- or 48-inch soil layer. In this project, a total of 33 different site-treatment combinations were sampled where litter had been stored for at least 90 days. Assuming a stockpile size of 100 tons of litter, the amounts of inorganic N (i.e., ammonium-N + nitrate-N) found in the soil ranged from 2 to 29 pounds with a mean of 12 pounds. This project also evaluated various covers and bases (i.e., something under the litter). None of the covers or bases resulted in a significant reduction in nutrient losses from the poultry litter piles. During the three years of this project, there were four direct comparisons of using a polyethylene cover versus using no cover. The results showed that on average the no-cover treatments lost 16 pounds of inorganic N, while the polyethylene cover was not significantly different and lost an average of 13 pounds of inorganic N. Soluble salt levels in the surface layer of the soil following poultry litter storage usually prevented establishment of crops in the area were the litter was piled. Covering the pile with polyethylene did not reduce the amounts of soluble salts found in the soil. The nutrient lost in the greatest amounts from poultry litter piles was potassium followed by sulfur. Regression analysis showed that these two nutrients were the main contributors to high levels of soluble salts, and inorganic N levels had nearly zero impact on soluble salt concentrations. The poultry litter piles had only minimal impacts on soil test phosphorus concentrations. Overall, the results from this project showed that amounts of N lost from temporary piles of poultry litter were quite small and represented about 0.2% of the amount of N in the litter pile. These findings suggest that properly shaped poultry litter piles have less potential for nutrient losses than poultry litter spread on the soil at the wrong time of the year (i.e., in the fall or early winter prior to crop establishment). In other words, poultry litter storage requirements should not promote litter applications at inappropriate times of the year.

Finally, Delaware regulations on temporary in-field storage of poultry litter should be considered best management practices (BMPs) and should be followed.

ACKNOWLEDGEMENTS

We would like to thank Extension Associates, Shawn Tingle and Warren Willey, for their dedicated efforts in completing this project. We would also like to thank all the farmers who assisted with this project on their farms. Finally, we would like to thank the Delaware Nutrient Management Commission and the Delaware Natural Resources and Conservation Service for funding this project.

Background and Justification

The poultry industry on Delmarva is facing unprecedented challenges. Environmental issues related to water and air quality are a high priority. The challenge to the industry is the adoption of sound, practical and cost-effective technologies that protect the environment. These technologies must be phased-in to meet both current and future issues in a manner that does not jeopardize the industry’s competitiveness in national and international markets. Using best available management practices for temporary storage of poultry litter is a challenge that is currently facing the poultry industry. In fact, temporary storage of poultry litter has been identified by the Delaware Nutrient Management Commission (DNMC) as a priority initiative for nutrient management research and education needs within the state of Delaware (DNMC Annual Report, 2004). At a DNMC meeting on November 9, 2004 at the Delaware Department of Agriculture, temporary storage of poultry litter was identified as one of the most pressing issues facing agriculture in Delaware, and there was unanimous agreement that research using production-size stockpiles was needed for implementing best management practices (BMPs) that minimize nutrient loss potential. This meeting included individuals from the poultry industry, farmers, consultants, University of Delaware research and extension personnel, the director of DNREC’s Water Resources Division, NRCS personnel, DDA personnel, and other citizens concerned with water quality/nutrient management issues in Delaware.

There has been considerable research done with temporary storage of poultry litter in relatively small piles; however, we can find no work that has evaluated or demonstrated the impact of stockpiling BMPs when poultry litter is stored in piles the size that are used in production agriculture. A typical stockpile on Delmarva from a whole-house cleanout typically will contain from 75 to 200 tons of litter. During the summer of 2004, Bud Malone organized a “meeting of the minds” of individuals throughout all of North America who had conducted research and demonstration projects. The bottom-line finding from this workshop was that most research and demonstration work has been done on piles with eight to ten tons of litter and that no projects have ever evaluated BMPs and nutrient losses from poultry litter that is temporarily stored in stockpiles the size of those used in production agriculture.

New EPA standards indicate that stockpiles of litter that remain in the field for more than 14 days should be covered. Covering a pile with polyethylene is a recommended practice for litter that is stored outside beyond 14 days. However, farmers who have tried covering litter piles in polyethylene suggest that this practice is not practical. Their experiences indicate that piles covered in polyethylene require almost constant upkeep and monitoring and are costly to maintain. In addition, there is evidence that nutrient loading may not be reduced by covering poultry litter piles with polyethylene. Farmers have also reported that a wet, offensive layer of litter sometimes occurs on the surface of the covered pile.

Discussions with many of those involved in production agriculture who use poultry litter as a fertilizer have stated that it will be nearly impossible for them to store litter for less than 14 days in the field. Therefore, they will be forced to stop using litter, thereby creating a greater surplus of litter that will need to be exported from the area. Another major concern of this 14-day limit on stockpiling is that some growers will likely spread the litter on their fields regardless of the time of year. Obviously, spreading the litter without regard to the time of year (i.e., winter) is a practice that greatly increases the risk of nutrient losses to the environment.

Objectives

The main objective of this project was to determine best management practices for minimizing nutrient losses during temporary outdoor storage of poultry litter. The primary tasks were:

1)  To evaluate duration of poultry litter temporary storage

2)  To evaluate type of cover during temporary storage of litter

3)  To evaluate type of base (i.e., treatment applied under the litter pile) for use during temporary storage of litter

 

Methodology

Time of Removal:

This project began in the fall of 2005 by creating a large pile (approximately 350 tons) of poultry litter at a farm in Sussex County, DE. The pile was defined as Site TR1 and was setup as shown in Diagram 1 below:

Chart Graph Placeholder

Diagram 1. An 8-ft wide buffer (B) area was placed between treatments to eliminate possible treatments impacting each other.

Each buffer area was eight feet in length, while each treatment area was 16 feet in length. The width of the pile was about 20 feet and the height was about 6.5 feet. There were six planned treatments that were to remove the litter at 15 days, 30 days, 45 days, 90 days, 135 days, and 180 days after the pile was created. The pile required 14 tractor-trailer loads (each load contained about 25 tons) of litter, and this litter was dumped at the site from October 28 to October 31. The pile was pushed up into an “A” shape on 1 November 2005. The pile was positioned in a north-south orientation. The poultry litter was removed on the following dates: 17 Nov 2005, 2 Dec 2005, 14 Dec 2005, 2 Feb 2006, 20 Mar 2006, and 5 May 5 2006. These removal dates corresponding to the following number of days from initiation of the pile: 16, 31, 43, 93, 139, and 185 days, respectively.

This time of removal study was repeated by putting out another large pile in the fall of 2006 on a different farm in Sussex County; this site was defined as Site TR2. This pile was pushed up and started on 25 Oct 2006. Because of weather challenges and schedule conflicts with the cooperator, the removal dates did not coincide with those used in the first year at Site TR1. At Site TR2, the six removal dates were: 29 Nov 2006, 12 Dec 2006, 20 Feb 2007, 15 Mar 2007, 2 Apr 2007, and 8 May 2007. These removal dates corresponded to the following number of days from initiation of the pile: 35, 48, 118, 141, 159, and 195 days, respectively. Because the number of days from initiation of the pile to removal of the litter is different between the two sites, the treatments will be designated as R1, R2, R3, R4, R5, and R6 throughout this report.

Covers and Bases:

In the fall of 2005, a large litter pile was constructed on a different farm from Site TR1. The pile was defined as Site CB and was created as shown in Diagram 1; however, this pile contained seven treatments that were: 1) no cover, 2) polyethylene cover, 3) bentonite clay base, 4) spray- on carbon material at single rate, 5) spray-on carbon material at double rate, 6) sawdust base, and 7) Poultry Guard®, a litter treatment for ammonia control, spread on the soil as a base before piling the litter. This pile was created by dumping about 16 tractor-trailer loads of poultry litter on October 25 and October 26. On 27 October 2005, this pile was pushed up into an “A” shape that was nearly seven feet high (see Picture 1 for an image of the pile at Site CB).

Picture Placeholder

Picture 1. Site CB showing the no-cover treatment in the front, then the poly cover, then the bentonite base, then the two spray-on carbon treatments, then the sawdust treatment, and the Poultry Guard®-base treatment at the far end of the pile.

At Site CB, the base treatments were applied the morning of October 26 before the first load of litter was hauled in. The sawdust treatment was applied onto the soil surface to a depth of about four inches, while 100 pounds of bentonite clay was applied to an area that was 14 ft by 16 ft. The Poultry Guard was applied in a granular form at a rate of 50 pounds to an area that was 14 ft by 16 ft. Poultry Guard® is granulated clay impregnated with sulfuric acid that is used in poultry production houses for ammonia control. Unfortunately, the bentonite clay, Poultry Guard, and sawdust did not completely cover the area under the pile because the width of the pile was about 18 feet. All soil samples that were taken “under” the pile were collected from a treated area but the “edge” samples were not from a treated area. The spray-on carbon material was from a company in North Carolina that used this material as a bedding in poultry houses. The spray-on carbon material was applied on November 11. The two treatment areas where the carbon material was applied were covered with polyethylene from 27 Oct through 11 Nov. The material was sprayed on by employees of this North Carolina company. The contact person from this company was Timothy Cathey. The rates were applied as recommended by Mr. Cathey, which involved putting on his recommended rate for both treatment areas. On the “double” treatment area, a second layer of the material was applied so that it had double the thickness of the single rate treatment. This pile was positioned in a north-south orientation. The litter from all seven treatments was removed on March 27, 2006.

In the second year of this project, the cover and base study was changed based on the results from the first year. At one site (Site HM), four treatments were established in the same manner as in the first year. The four treatments were: 1) no cover, 2) polyethylene cover, 3) Soiltac® at 110 sq ft/gal, and 4) Soiltac at 220 sq ft/gal. Soiltac® is a product marketed by company called Soilworks® that is located in Gilbert, AZ (their web site is http://www.soilworks.com). Soiltac is polymer-based emulsion that is used to stabilize soil banks to prevent erosion. This material was sprayed on as a cover over the litter using a hand-held sprayer. The same four treatments were replicated at an additional site (Site GT), which was located in Sussex County near the Georgetown airport. A different set of four treatments were used at another site (Site LS) in western Sussex County; the four treatments were: 1) no cover or base, 2) spray-on as a cover of the Illinois Silage material, 3) Soiltac sprayed on the soil as a base at a rate of 220 sq ft/gal, and 4) sawdust applied as a base. The Illinois silage cover is a recipe developed by Dr. Larry Berger at the University of Illinois using primarily ground wheat and salt. This product was developed to spray on silage to protect it during storage that can then be fed directly to animals when the silage is fed. The Soiltac and the sawdust treatments were both applied so that the entire area under the pile was treated, including the edges of the pile. The sawdust was applied so that it was about four inches thick on the surface of the soil before the litter was applied on top of it.

At Site HM, the litter was piled and pushed into a conical shape on November 20, 2006 and the covers were applied on November 21; the litter was removed on March 23, 2007. At Site GT, the pile was created on December 14, 2006, the poly cover was applied on December 15, and the Soiltac covers were applied on December 19; the litter was removed May 11, 2007. At Site LS, the litter was piled and pushed into a conical shape on January 22, 2007, and the pile was removed on May 18, 2007.

In the third year of this project, an additional study was conducted to evaluate the effect of covering and to be sure that the methods used with the poly covers in the first two years were appropriate methodology. In the first two years of this study, the poly cover was only applied to a portion of a large pile due to the way the study was designed (see Diagram 1 and Picture 1). In a production agriculture field, the entire pile would be covered. Therefore, in the third year, three large piles were created in one field on a farm in Sussex County. One pile was left uncovered, one was covered with black poly, and the third pile was covered with a material called Compostex®, which is a breathable cover that is designed to keep water out but air can move through the material and it is used for composting various materials. The two piles that were covered were completely covered (see Picture 2 for an example). These piles were created on 10 November 2007 and each pile contained about 150 tons of poultry litter. The piles were removed on 19 March 2008.

Picture Placeholder

Picture 2. This is the poly-covered pile in 2008.

Soil Sampling

For all studies in all years, soil samples were taken from each treatment area within one day of the litter being removed from the soil. For most piles, soil samples were taken again about 30 to 45 days later, and then samples were taken again about 70 to 90 days after the litter was removed. The reason for taking these additional samples was to determine if there was additional loading of nutrients from the litter that was not completely removed from each treatment area. In the first year of the project, soil samples were taken from the following depths: 0 to 6, 6 to 12, 12 to 24, and 24 to 36 inches. During the second year of the project, the same depths were sampled plus the 36- to 48-inch depth was sampled. In the third year of the project, the sampling depths were the same as the second year but the 0- to 6- and 6- to 12- inch depths were taken as one sample (i.e., 0 to 12 inches).

During the first year of the project, soil samples were taken by taking five cores from each sample area and compositing these into one sample for each depth. A 1-inch diameter soil probe was used for the surface 24 inches of soil, while a 0.5-inch probe was used for the 24- to 36-inch layer. The spring of 2006 was quite dry and it became nearly impossible to push the soil probe into the soil so beginning with the 180-day removal treatment and for Site CB, a three- inch diameter bucket auger was used for taking the samples. The bucket auger was used in the second and third year studies. With the bucket auger, only one core was taken per sampling area due to the large volume of the soil that was collected and the length of time required for taking the samples. To prevent water and soil from washing into the soil sampling holes, all holes were filled with bentonite clay immediately after the soil samples were taken.

For the first-year studies, nine separate areas were sampled within each treatment area. The sampling locations were the following: 15 and 30 feet outside the pile on both the east and west side (four sample locations), the edge of the pile on both the east and west side (two sample locations), directly under the peak of the pile (one sample), three feet to the east of the peak (one sample), and three feet to the west of the peak (one sample).

For the second year of the project, based on the first year’s results, the sampling pattern was changed. The second-year pattern involved taking ten sampling points from each treatment in the following way: 20 feet outside the pile on both sides of the pile (two sampling points), two feet outside from the edge of the pile on both sides (two sampling points), both edges of the pile (two sampling points), two feet inside from the edge of the pile on both sides (i.e., two sampling points that were both under the pile), and then two feet on either side of the center peak of the pile (i.e., two sampling points that were both under the pile).

In the third year, the soil samples were taken from 13 points where the pile was located. The 13 sampling points were sampled in the following way: 20 feet outside the pile on both sides of the pile (two sampling points), four feet outside from the edge of the pile on both sides (two sampling points), two feet outside from the edge of the pile on both sides (two sampling points), both edges of the pile (two sampling points), two feet inside from the edge of the pile on both sides (i.e., two sampling points that were both under the pile), four feet inside from the edge of the pile on both sides (i.e., two sampling points that were both under the pile),and then one sample from directly under the peak of the pile (one sample point). This sampling pattern was done twice across line transects perpendicular to the line of the pile, so there were a total of 26 sampling points.

For each year of the study, all soil samples were immediately and rapidly air-dried in a greenhouse. The samples were then ground to pass a 2-mm sieve and sent to the laboratory for analyses. Mehlich III (M3) analyses were performed as follows: 1 g of soil was mixed with 10 ml of the extracting solution (0.2 M CH3COOH + 0.25 M NH4NO3 + 0.015 M NH4F + 0.013 M HNO+ 0.001 M EDTA) for 5 min. and filtered through Whatman #42 filter paper (Mehlich, 1984). The M3 extracts were analyzed by inductively coupled plasma atomic emission spectroscopy (ICP- AES). Soluble salts were determined as described by Sims and Heckendorn, 1991. Nitrate and ammonium were determined using the 2M KCl procedure as described by Sims and Heckentorn, 1991. Mehlich III and soluble salts were measured only on soil samples from the surface twelve inches, while nitrate and ammonium were determined on all soil samples. For the 2008 studies (i.e., Year 3), the soil samples were only analyzed for nitrate and ammonium. All soil analyses were performed by the University of Delaware Soil Testing Laboratory. The following estimated soil bulk densities were used for each of the sampling depths (0-6”, 6-12”, 12-24”, 24-36”, and 36-48”) when calculating total amounts of nutrient in the soil: 1.30, 1.32, 1.34, 1.36, and 1.38 grams per cubic centimeter of soil, respectively.

Poultry Litter Sampling and Analyses

The poultry litter that was used for all piles was sampled when the pile was created and when the pile was removed by taking several small grab samples using a shovel. At the time of litter removal, separate samples were taken from the wet layer on the outside of the litter and the dry litter in the middle of the pile (see Picture 3 for view of the “wet” layer). The grab samples were placed in a bucket and mixed thoroughly. A subsample was taken and placed in a sealed plastic Ziploc® bag and immediately placed in a refrigerated room until analyzed by the laboratory.

Each treatment area within each pile had at least three separate samples taken. All manure samples were analyzed by the Delaware Department of Agriculture Manure Testing Laboratory. All litter samples were analyzed for total N, ammonia N, calcium, magnesium, sulfur, copper, zinc, manganese, boron, ash content, and moisture content. This laboratory is certified through the Manure Analysis Proficiency (MAP) Program that is administered through the Minnesota Department of Agriculture.

Runoff Collection System

For all three years of this study, a runoff collection system was built that was designed to catch any runoff and leachate coming out of the pile. The runoff system was installed when the pile was pushed up and left in place for about 185 days at Site TR1 and 195 days at Site TR2. For the third year, manure was pushed up on January 12, 2008 and the pile was removed on March 23, 2008; the runoff system was in place this entire time and this pile was defined as Site T3. It is assumed that when piles are pushed up into an “A” shape that water will run off the edges of the pile and then move into the underlying soil along these edges of the pile. Visual observations suggest that approximately the outside three feet of the pile (see Picture 3 for an example) will become saturated after enough rainfall has occurred and then this runoff and leachate will leach into the soil. The runoff system was designed with the goal of capturing all of this runoff and leachate.

Stainless steel pans were built six feet in length and four feet in width with a four-inch tall edge around the pan. The pan was inserted about three feet and three inches into the pile, so the pan was collecting runoff from a six-foot length along the edge of the pile. A hole was drilled into the corner of the pan with a drainage tube that drained via gravity into a tank that was placed in a large hole that was dug next to the pile. A slanted roof was built over the portion of the pan that was not inserted into the pile to prevent rainfall from getting into the pan. A runoff system was installed on both the east and west side of the pile so that data were collected from two places in the pile for each year. After each runoff event, the total leachate volume was measured and subsamples were taken from the leachate and immediately frozen. The frozen samples were transported to the University of Delaware Soil Testing Laboratory. Once at the laboratory, the samples were thawed and immediately analyzed for total nutrient (N, P, and K) content.

Site Descriptions

All piles in this study were located on soils with less than 1% slope. The soil texture at Sites LS and NPS were sandy loam, while the texture for all other sites was loamy sand.

Weather Information

Several automatic weather stations in the area were used to collect weather data and rain gauges were used at the runoff sites to collect rainfall amounts. Also, the temperature of some piles was monitored with automatic data loggers, however, much of the temperature data were lost due to system malfunctions. In some cases, temperature data were collected and recorded.

Picture Placeholder

Picture 3. This illustrates how the wet layer forms on top of the pile and along the edges of the pile. This image was taken on 2 Feb 2006 from a pile that was created on 1 Nov 2005; this pile had received 9.8 inches of rain since 1 Nov 2005.

Results and Discussion

Rainfall amounts during the three years of this study are shown in Figure 1a. The rainfall patterns were near normal for Sussex County with the exception of the period from February 13 through April 1 of year 1, which was extremely dry. The average daily temperatures followed similar patterns each year of this study (Figure 1b). Rainfall amounts were collected with manual rain gauges at each site where the runoff-collection systems were installed and these amounts are shown in Tables 1, 2, and 3. The total amount of runoff collected for each runoff event is also presented in Tables 1, 2, and 3.

The poultry litter for all projects came directly from local poultry houses and was from total cleanouts. The litter used in these projects came from different houses.  In fact, for the very large piles, the litter within the piles was sometimes from more than one house. The nutrient concentrations tended to vary within the same pile (Tables 4 through 11). For example, for the time of removal study in year 1, the total N concentration was 36 lb N/ton of litter in the Day 15 treatment but was 62 lb N/ton of litter in the Day 90 treatment (Table 5). This variability probably represents variability within the house or possibly different houses rather than variability within the immediate position within the pile because each value in Tables 4 through 11 represents a mean of at least three separate samples that came from the same part of the large pile. The variability among samples taken from the same point is much less than the variability among the treatment areas within the large pile. The concentrations of boron, manganese, copper, and zinc for all manure samples are presented in Tables 12 through 19.

Runoff Study

The concentration of nutrients in the runoff samples was always highest for the first runoff event in all three years (Figures 2, 3, and 4). After the first one to two runoff events, the concentration of ammonium, P, and K tended to be somewhat consistent. Although the concentrations seemed rather high, it is important to evaluate the total amounts of nutrient being lost from the piles. The total ammonium-N lost each year ranged from about 0.3 to 0.5 pounds of N (Figure 5). This represents a six-foot length of the pile. In order to convert these values to pounds of nutrient per area of land, a specific pile size is needed. Therefore, for this calculation and for all similar calculations throughout this report, a pile size of 100 feet in length and 18 feet in width will be used. A pile with this size footprint that was 6.5 feet tall should contain a little over 100 tons of poultry litter. Based on the observed concentrations of N in the leachate and this assumed pile size, the average amount of ammonium-N lost from the six replications over the three years of this study was 16.3 lbs. (Figure 8). Minimal amounts of nitrate-N were found in the leachate, in fact, for most leaching/runoff events the amount of nitrate-N that was lost was near zero. The average amount of nitrate-N lost from the litter over the three years of this study was 0.8 lbs (Figure 8).

The average amount of total P for the three years of this study that was found in the leachate was 3.5 lbs, while the amounts of dissolved P averaged 0.8 lbs (Figure 9). The nutrient that was lost in the greatest amounts from all six replications was K, and the average amount of K in the leachate was 113 lbs (Figure 10). Sulfur was also an important nutrient in terms of amounts found in the leachate. Although the amounts of S lost from the piles were much less than the amounts of K, the amounts of S were about double the amounts of N lost from the piles. The average amount of S lost in the leachate was 32 lbs (Figure 10).

Cover and Base Study: Nitrogen in Soil

In Year 1 at Site CB, the concentration of inorganic N (ammonium-N PLUS nitrate-N) tended to be higher along the edge of the pile than directly under the middle of the pile (Table 20). These data also show that inorganic N did leave the poultry litter and entered into the soil (i.e., compare 30 feet outside the pile to the edge and under the pile). An observation that was surprising was the concentration of inorganic N in the soil under the poly-covered treatment. Not only did nitrogen leave the litter from the pile that was covered with poly, but these data suggest that more N was lost from the poly-covered treatment than was lost from the treatment that had no cover. Soil samples were taken again from each of these treatment areas 51 days after the piles were removed (Table 21). These samples taken 51 days later show the same trends as the initial samples suggesting that the poly-covered treatment lost more N than the no-cover treatment. It is important, however, to remember that these data represent only one replication. The other five treatments in this project (i.e., bentonite-clay base, spray-on carbon at two rates, sawdust base, and the Poultry Guard base appeared to provide no significant reduction in nutrient loading to the soil when compared to the no-cover treatment.

There were several important observations that should be documented from these various treatments. First of all, the bentonite clay was applied at a rate that seemed economically practical. After it was applied, it was assumed that the material would swell and the rate would be adequate. Our observations suggest that the rate should probably be doubled from what we used. A bigger problem, however, with the bentonite clay was that once applied to the ground it became very sticky. Because growers typically drive a large truck across the soil as they are dumping the litter into the pile, the tires from the truck tend to destroy the bentonite clay layer and the bentonite sticks to the truck tires. The spray-on carbon material sealed up well after it was sprayed onto the piles, however, after a few weeks the material began to crack. After five months, the material had an extreme number of cracks and parts of the material had even blown off in the wind. The litter under the spray-on cover smelled worse and was harder to work with than the treatment that had no cover. An interesting observation from the sawdust treatment was that the sawdust under the pile had the same appearance and feel as it did the day it was placed at the site. It was not soggy and felt as if the moisture content was nearly the same as when it was first placed at the site. There were no visual signs of decomposition. This observation suggests that little, if any, water moved out of the pile and that the concentration of oxygen was limiting under the pile because the sawdust had not started to decompose. Nothing unusual or important was noted about the Poultry Guard treatment.

In the second year of this project, the covers and bases were evaluated at more locations with a smaller pile size (in terms of length, not height or width) because it was difficult to find growers who wanted to create such a large pile. Also, this allowed more replication of some of the treatments. The poly cover treatment was applied at two sites in the second year of the project (Site HM and Site GT). At these two sites, the poly cover treatments did have elevated concentrations of inorganic N relative to the area that was outside the pile (i.e., 20 ft out); however, the N levels under the poly cover treatments were not higher than the no-cover treatments as observed in the Year 1 study (Tables 22 and 23). Nonetheless, these data, along with the data from Year 1 of the study, suggest that using a poly cover provides no advantage in reducing N losses from the pile when compared to applying no cover. The data from these poly covered treatments suggest that the N could be entering into the soil as ammonia gas. The temperature of the litter under the poly cover is typically hotter than when no cover is used, which may convert more of the N in the litter to ammonia. This could explain why the inorganic N levels were higher under the poly in the first year of the study. For example, in the first-year study at Site CB, the temperature at two feet down in the pile on 20 Mar 2006 was 63.9°F under the no-cover treatment and 109.2°F under the poly cover treatment.

As mentioned previously, there was concern that the design of the project was different than how a pile would be covered in a production field. Therefore, in 2008, an additional study was done where the entire piles were covered. The results indicate that the inorganic N levels where the entire pile was covered show no trend for the poly cover to have higher inorganic N levels in the soil than the no-cover treatment (Table 24). These data, however, are similar to the previous data that suggest there is no environmental benefit to covering the pile. In addition, the breathable cover (i.e., Compostex) appears to be similar as the poly cover in that losses of inorganic N from the litter pile into the underlying soil did occur. In this 2008 project, a second set of soil samples were taken on June 3rd, however, the flags that were used to mark the pile locations were dislocated by the farming equipment for all three piles. In most cases the location of a previous poultry litter pile can still be located several weeks after the litter has been removed because of limited, if any, crop growth; however, there was an excellent stand of corn where all three piles had been located at Site NPC. This excellent stand of corn occurred most likely because of the aggressive tillage by the farmer after the piles were removed, thereby, thoroughly mixing the salts into the soil and allowing the corn seed to geminate and the seedlings to grow. As a result, it is possible that the samples were not taken from the exact locations intended, so the results in Table 24a should be used with caution. For the results shown in Table 24a, all soil samples were taken from within the cornfield, and these samples were taken when PSNT samples would be taken (i.e., 12-inch tall corn).

During the second year of this project, several other options were evaluated as possible alternatives that may reduce nutrient losses from a poultry litter pile. Our observations suggest that the Soiltac does not provide a benefit because the inorganic N levels were similar to the no- cover treatment regardless of the Soiltac treatment (Tables 22, 23, and 25). This finding is not surprising because the Soiltac tended to crack after a few weeks of spraying it onto either the poultry litter or the soil. The Illinois Silage treatment was also not a good alternative, in fact, this treatment didn’t work at all (Table 25). The treatment completely fell apart and cracked. One of the challenges with the Illinois Silage treatment is that when this is used on silage piles a tractor is used to pack down the material. This packing process is really not an option for a poultry litter pile because the sides of the pile are too steep. Based on the observations that have been found with the poly cover for the three years of this project and assuming that much of the N is moving into the soil as ammonia gas, it seems unlikely that any cover could be used to prevent inorganic N from leaving the pile and getting into the underlying soil.

During the second year of this project, three additional piles were sampled on three different farms that were piled in an “A” shape and were at least six feet tall. In fact, the pile at Site WI was about 14 feet tall, was piled onto heavy cornstalk residue, and contained 245 tons of litter. The inorganic N concentrations in the soil indicate that N moved from these piles into the underlying soil, however, it is important to note the concentrations of inorganic N found 20 feet outside the pile (Table 26) because these concentrations were not influenced by the pile. Even though it is apparent that N did move out of these three piles into the underlying soil, the amounts of N that moved out of the piles were quite small.

Time of Removal Studies: Nitrogen in Soil

In Year 1, Site TB1 showed that some inorganic N had entered into the soil within 15 days (Table 27). In Year 2, Site TB2 did not have a 15-day treatment, but the first removal date (i.e, 35 days) showed again that some inorganic N had entered into the soil within 35 days (Table 28). Interestingly, at Site TB1, there was little rain on the litter pile prior to the 15-day treatment being removed. Because inorganic N was present in the soil after this treatment was removed, this supports the idea that ammonia gas may be the primary pathway for N movement from the litter into the underlying soil. These data at Site TB1 show that the inorganic N levels in the soil were higher for the 30-day removal treatment than for the 15-day removal. There was significant movement of inorganic N to the lower soil depths for some treatments. In most cases, the primary form of inorganic N present in the soil under the piles was ammonium (see Tables 29 through 32 for examples).

To put these concentrations into perspective, the concentrations were converted to pounds of N. To make this conversion, the same land area was assumed as with the runoff data: 100 feet wide and 18 feet long. The assumed bulk densities used for converting concentrations to pounds of nutrient were provided above. Using these assumptions at Site TB1, the amounts of inorganic N ranged from a low of 4 lbs for the 16-day removal treatment to a high of 12 pounds for the 31-day treatment, while the 185-day removal treatment had 10 lbs of inorganic N in the soil (Figure 11).  For Site TB2, the first removal was the 35-day treatment and there were 4 lbs of inorganic N found in this treatment, while the 195-day treatment contained 16 lbs of inorganic N in the underlying soil (Figure 11). The most surprising observation from these two replications of data for the time-of-removal study was the relatively small amounts of inorganic N found in the soil after 180-days of litter storage (Figure 11).

Summary of Soil Nitrogen Data from all Samplings

During the time period of this study, there were 33 separate site-treatment combinations where litter was piled for at least 90 days. All 33 site-treatment combinations had soil samples taken following litter removal. In all cases, soil samples were taken from the area affected by the litter and an area outside the pile that was not affected by the litter so that a total loading from the litter could be calculated. Using the assumed pile size provided above, the amount of inorganic N that moved out of the litter and was found in the underlying soil ranged from 2 to 29 lbs with a mean of 12 lbs (Figure 12). It is interesting to note that there was no significant correlation between the amounts of N found in the soil under the piles and the concentrations of N found in the poultry litter that was piled at the site (Figure 13).

A poultry litter pile that is 6.5 tall, 100 feet long, and 18 feet wide would contain at least 100 tons of litter, which would correspond to about 5,500 pounds of N (assuming 55 lb N/ton) in that pile. As a result, the data from these 33 site-treatment combinations suggest that about 0.2% of the N in a properly shaped pile will be lost from the pile to the environment. This amount of N is insignificant compared to the amount of N that could potentially be lost to the environment from 5,500 pounds of N spread as poultry litter during the wrong time of the year. In other words, the results of this research demonstrate that relatively small amounts of N are lost from properly- shaped piles, and therefore, if poultry litter must be kept in temporary field storage piles, it should be kept in the pile until the recommended time of spreading for the crop to be grown regardless of how many days the poultry litter pile has been in place. These results, however, do not support storing poultry litter in temporary piles from one growing season to the next.

Within these 33 site-treatments, there were four side-by-side comparisons of a polyethylene covered pile next to a pile with no cover. The average amount of inorganic N in the soil under the four poly covered piles was 13 lbs, while the average under the no-cover pile was 16 lbs. Because there was no significant difference in amounts of N found in the underlying soil between the poly covered and no-cover piles, this suggests that N is moving from the litter into the soil as ammonia. Regardless of the method of movement, covering poultry litter piles with polyethylene does little to reduce the amounts of N leaving the litter and moving into the soil.

The overall average increases in inorganic N throughout soil profile under the litter piles for all 33 site-treatment combinations were 39.1, 19.4, 15.2, and 6.7 mg N/kg for the depths of 0-12, 12-24, 24-36, and 36-48 inches, respectively. When converted to pounds and assuming a 100 ft by 18 ft pile size, these values were 5.8, 2.9, 2.3, and 1.0 pounds for the 0-12, 12-24, 24-36, and 36-48 inch depths, respectively. This shows that about 75% of the N in the soil under the pile was in the top 24 inches of soil. Therefore, if a crop could be established in the area where the pile was located, it is likely that a significant portion of this N could be utilized by the growing crop and not lost to the environment.

Phosphorus in Soil

All sites used for this study tended to have high concentrations of Mehlich 3-P in the soil, which is not surprising because these farms all have long-term histories of using poultry litter. In general, the soil test P data from these sites suggest that the poultry litter piles are not having much of an impact on soil test P (Tables 33 through 39). There were instances where the soil test P concentration where the litter was piled were higher than the concentration of soil test P where no litter was piled (e.g., Table 33) , but at most locations it is difficult to see an affect of the litter pile on soil test P. At one site (Table 36), the soil test P levels in the soil where the pile was located appear to be greater than outside the pile area; however, it should be noted that the samples taken 20 feet outside where the pile was located were actually taken in a grassy area outside the field. Therefore, the high P concentrations where the pile was located may or may not be a result of the litter pile. It’s possible that the higher concentrations may simply be a result of past management in this area.

Potassium, Sulfur, and Soluble Salts in Soil

The soil test data show that large amounts of potassium are entering into the soil where the poultry litter was piled (Table 40 through 46). These results show great variability in the magnitude of the increase in soil test K in the area under the pile relative to the area outside where the pile was located, but it is clear from these soil analyses that the nutrient that is being lost in the greatest quantities by several orders of magnitude is potassium. This finding is similar to what was found in the runoff that was collected from the poultry litter piles.

The soluble salt concentrations in the surface layer of the soil where the litter was piled were often significantly above the level considered safe for growing crops, which is about 1 mmhos/cm (Tables 47 through 53). These high levels of soluble salts explain why farmers often are unable to establish a crop in these areas. The high soluble salts either prevent the seed from germinating or kill the young plant after it germinates because the roots are destroyed from the high concentrations of salts (see Picture 4).

The high concentrations of potassium in the soil where poultry litter has been piled appear to be one of the main contributors to the soluble salt concentrations in the soil. The relationship between soil potassium concentration and soluble salts shows that soil K accounts for 92% and 82% of the variability in soluble salts for the two years of this study, while soil S accounts for 93% and 82% (Figure 8). The relationships between soil ammonium and soil nitrate concentrations with soluble salt concentrations suggest that these two nutrient forms had little effect on the observed soluble salt concentrations (Figure 9). The concentrations of Mehlich-3 sulfur for each site are presented in Tables 54 through 60.

Other Nutrients in Soil

Because the Mehlich-3 procedure was used to measure concentrations of P and K in the soil, several other nutrients were automatically included in the analyses so these concentrations are being presented in this report for informational purposes. These other nutrients included calcium {(Ca) Tables 61 through 67}, magnesium {(Mg) Tables 68 through 74}, copper {(Cu) Tables 75 through 81}, manganese {(Mn) Tables 82 through 88}, and zinc {(Zn) Tables 89 through 95}. It appears that the poultry litter had only slight, if any, influence on the concentrations of these nutrients in the underlying soil.

Picture Placeholder

Picture 4. Image taken on 26 Sept 2006 from a site where poultry litter was piled during the winter of 2005/2006 that shows the lack of soybeans growing in the area.

Summary and Conclusions

1)    Using a poly cover did not reduce nutrient losses from field-size poultry litter piles to the underlying soil.

2)    Potassium was the nutrient lost in the largest amounts from the piles to the environment.

3)    Potassium and sulfur were the two nutrients that caused the high soluble salt concentrations in the soil where the piles were located.

4)    Phosphorus losses from poultry litter piles were small.

5)    Potassium losses from poultry litter piles were about eight times greater than N losses.

6)    On average, a 100-ton pile of poultry litter lost 12 pounds of nitrogen, which is a relatively small amount of N.

7)    About 75% of the N that moved into the underlying soil from the poultry litter was in the surface 24 inches of soil, so establishment of a crop in the area of the pile would remove a significant portion of this N from the soil.

8)    Sawdust, Poultry Guard®, bentonite clay, Soiltac®, and spray-on carbon materials provided no benefit in terms of reducing nutrient losses from the pile to the environment.

9)    The amount of N leaving properly-shaped poultry litter piles and moving into the underlying soil was only about 0.2% of the amount of N in the poultry litter.

10) Litter spread at the wrong time of the year would have a much greater risk of nutrient loss than litter kept in a pile.

11) If litter must be stored in the field, it should be kept in a pile until the appropriate spreading time for the crop to be grown.

12) Recommendations that promote spreading litter sooner than is optimal for crop production practices should be discouraged, because litter spread too early will have much greater risk of nutrient losses than litter kept in a properly-shaped litter pile.

13) In-field storage of poultry litter facilitates the transport of poultry litter from areas with high concentrations of poultry litter to areas where there is a low concentration of poultry litter available for use during crop production.

14) Current Delaware regulations on temporary stockpiling of poultry litter should be considered best management practices (BMPs) and should be followed.

Chart Graph Placeholder

Chart Graph Placeholder

Figure 1. Cumulative rainfall (a) and average daily temperature (b) from November 1 to May 31 at the airport in Laurel, Delaware; project started in November 2005 and ended in May 2008.

Table 1. Rainfall amounts and runoff/leachate amounts collected in each tank during the 1st year of the study at Site TR1.

Chart Graph Placeholder

Table 2. Rainfall amounts and runoff/leachate amounts collected in each tank during the 2nd year of the study at Site TR2.

Chart Graph Placeholder

Table 3. Rainfall amounts and runoff/leachate amounts collected in each tank during the 3rd year of the study at Site T3.

Chart Graph Placeholder

Table 4. Nutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for each treatment during the 1st year of this study at Site CB.

Chart Graph Placeholder

Table 5. Nutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for the time of removal study at Site TR1.

Chart Graph Placeholder

Table 6. Nutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for each treatment during the 2nd year of this study at Site GT.

Chart Graph Placeholder

Table 7. Nutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for each treatment during the 2nd year of this study at Site HM.

Chart Graph Placeholder

Table 8. Nutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for each treatment during the 2nd year of this study at Site LS.

Chart Graph Placeholder

Table 9. Nutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for each treatment during the 2nd year of this study at three sites where no treatments were applied (i.e., these would be “no cover” piles).

Chart Graph Placeholder

Table 10. Nutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for each treatment during the 3rd year of this study at Site NPC.

Chart Graph Placeholder

Table 11. Nutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for the time-of-removal study at Site TR2.

Chart Graph Placeholder

Table 12. Micronutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for each treatment during the 1st year of this study at Site CB.

Chart Graph Placeholder

Table 13. Micronutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for the time of removal study during year 1 at Site TR1.

Chart Graph Placeholder

 

Table 14. Micronutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for each treatment during the 2nd year of this study at Site GT.

Chart Graph Placeholder

Table 15. Micronutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for each treatment during the 2nd year of this study at Site HM.

Chart Graph Placeholder

Table 16. Micronutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for each treatment during the 2nd year of this study at Site LS.

Chart Graph Placeholder

Table 17. Micronutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for the each treatment during the 2nd year of this study at three sites where no treatments were applied (i.e., these would be “no cover” piles).

Chart Graph Placeholder

Table 18. Micronutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for the each treatment during the 3rd year of this study at Site NPC.

 

Chart Graph Placeholder

Table 19. Nutrient concentrations in the poultry litter on the day the pile was initiated and the day the pile was removed for the time-of-removal study during year 2 at Site TR2 (i.e., 2006 to 2007).

Chart Graph Placeholder

Figure 2. Concentration of ammonium-N in the runoff/leachate for each year of the study.

Chart Graph Placeholder

Figure 3. Concentration of total P in the runoff/leachate for each year of the study.

Chart Graph Placeholder

Figure 4. Concentration of potassium in the runoff/leachate for each year of the study.

Chart Graph Placeholder

Figure 5. Cumulative amount of ammonium-N in the runoff/leachate for each year in a 6-ft length of the poultry litter pile.

 

Chart Graph Placeholder

Figure 6. Cumulative amount of total P in the runoff/leachate for each year in a 6-ft length of the poultry litter pile.

Chart Graph Placeholder

Figure 7. Cumulative amount of potassium in the runoff/leachate for each year in a 6-ft length of the poultry litter pile.

Chart Graph Placeholder

Figure 8. Total amounts of ammonium-N and nitrate-N in the runoff for each side of the pile in each year and the mean across all three years; total amounts are based on a pile size of 100 feet long and 18 feet wide.

Chart Graph Placeholder

Figure 9. Total amounts of total P and dissolved P in the runoff for each side of the pile in each year and the mean across all three years; total amounts are based on a pile size of 100 feet long and 18 feet wide

Chart Graph Placeholder

Figure 10. Total amounts of potassium and sulfur in the runoff for each side of the pile in each year and the mean across all three years; total amounts are based on a pile size of 100 feet long and 18 feet wide.

Table 20. Concentration of inorganic-N (nitrate-N + ammonium-N) after poultry litter was piled for 150 days on a Delaware farm in 2006 on the day after poultry litter was removed from Site CB.

Chart Graph Placeholder

Table 21. Concentration of inorganic-N (nitrate-N + ammonium-N) after poultry litter was piled for 150 days on a Delaware farm in 2006 fifty-one days after poultry litter was removed from Site CB.

Chart Graph Placeholder

Table 22. Concentration of inorganic-N (nitrate-N + ammonium-N) after poultry litter was piled for 150 days on a Delaware farm in 2007 on the day after poultry litter was removed from Site GT.

Chart Graph Placeholder

Table 23. Concentration of inorganic-N (nitrate-N + ammonium-N) after poultry litter was piled for 150 days on a Delaware farm in 2007 on the day after poultry litter was removed from Site HM.

Chart Graph Placeholder

Table 24. Concentration of inorganic-N (nitrate-N + ammonium-N) after poultry litter was piled for 90 days on a Delaware farm in 2008 on the day after poultry litter was removed from Site NPC.

Chart Graph Placeholder

Table 24a. Concentration of inorganic-N (nitrate-N +ammonium-N) after poultry litter was piled for 90 days on a Delaware farm in 2008; samples were taken when corn was 12-in tall (i.e., June 3, 2008) at Site NPC.

Chart Graph Placeholder

Table 25. Concentration of inorganic-N (nitrate-N + ammonium-N)  after poultry litter was piled for 150 days on a Delaware farm in 2007 on the day after poultry litter was removed from Site LS.

Chart Graph Placeholder

Table 26. Concentration of inorganic-N (nitrate-N + ammonium-N) after poultry litter was piled for 150 days on three Delaware farms in 2007 on the day after poultry litter was removed (sites had no treatments).

Chart Graph Placeholder

Table 27. Concentration of inorganic-N (nitrate-N + ammonium-N) after poultry litter was piled for 15 to 180 days on a Delaware farm in 2006 at Site TR1; samples were taken shortly after litter was removed.

Chart Graph Placeholder

Table 28. Concentration of inorganic-N (nitrate-N + ammonium-N) after poultry  litter was piled for 15 to 180 days on a Delaware farm in 2007 at Site TR2; samples were taken immediately after litter was removed.

Chart Graph Placeholder

Table 29. Concentration of ammonium-N after poultry litter was piled for 150 days on a Delaware farm in 2006 on the day after poultry litter was removed from Site CB.

Chart Graph Placeholder

Table 30. Concentration of ammonium-N in 2006 after poultry litter was piled for 150 days on a Delaware farm; samples taken 51 days after poultry litter was removed from Site CB.

Chart Graph Placeholder

Table 31. Concentration of ammonium-N after poultry litter was piled for 150 days on a Delaware farm in 2007 on the day after poultry litter was removed from Site GT.

Chart Graph Placeholder

Table 32. Concentration of ammonium-N after poultry litter was piled for 150 days on a Delaware farm in 2007 on the day after poultry litter was removed from Site HM.

Chart Graph Placeholder

Chart Graph Placeholder

Figure 11. Total amounts of inorganic N (nitrate-N + ammonium-N) found in the underlying soil after poultry litter was removed from Sites TB1 and TB2; number of days refers to the number of days the litter was in place before it was removed from the site. The total inorganic N amounts were based on a land area of 100 ft long and 18 ft wide.

Chart Graph Placeholder

Figure 12. Total amounts of inorganic N (nitrate-N + ammonium-N) found in the underlying soil after poultry litter was removed for 33 different site-treatment combinations that all had poultry litter piled for at least 90 days during the three years of this project. The total inorganic N amounts were based on a land area of 100 ft long and 18 ft wide.

Chart Graph Placeholder

Figure 13. Relationship between total amounts of inorganic N found in the underlying soil and amounts of N present in the poultry litter that was piled on the site; these data represent 33 site- treatment combinations that all had poultry litter piled for at least 90 days during the three years of this project. The total inorganic N amounts in the soil were based on a land area of 100 ft long and 18 ft wide.

Table 33. Concentration of Mehlich 3-P after poultry litter was piled for 150 days in 2006 on a Delaware farm; soil samples were taken 86 days after poultry litter was removed from Site CB.

Chart Graph Placeholder

Table 34. Concentration of Mehlich 3-P after poultry litter was piled for 150 days on a Delaware farm in 2007 immediately after poultry litter was removed from Site GT.

Chart Graph Placeholder

Table 35. Concentration of Mehlich 3-P after poultry litter was piled for 150 days on a Delaware farm in 2007 immediately after poultry litter was removed from Site HM.

Chart Graph Placeholder

Table 36. Concentration of Mehlich 3-P after poultry litter was piled for 150 days on a Delaware farm in 2007 immediately after poultry litter was removed from Site LS.

Chart Graph Placeholder

Table 37. Concentration of Mehlich 3-P after poultry litter was piled for 150 days on three Delaware farm in 2007 immediately after poultry litter was removed (sites had no treatments).

Chart Graph Placeholder

Table 38. Concentration of Mehlich 3-P in the soil after poultry litter was piled for 15 to 180 days in 2006 at Site TR1; soil samples were taken the same day the poultry litter was removed.

Chart Graph Placeholder

Table 39. Concentration of Mehlich 3-P in the soil after poultry litter was piled for 15 to 180 days in 2007 at Site TR2; soil samples were taken the same day the poultry litter was removed.

Chart Graph Placeholder

Table 40. Concentration of Mehlich 3-K in the soil after poultry litter was piled for 150 days in 2006 at Site CB; soil samples were taken one day after poultry litter was removed from the site.

Chart Graph Placeholder

Table 41. Concentration of Mehlich 3-K in the soil after poultry litter was piled for 150 days in 2007 at Site GT ; soil samples were taken one day after poultry litter was removed from the site.

Chart Graph Placeholder

Table 42. Concentration of Mehlich 3-K in the soil after poultry litter was piled for 150 days in 2007 at Site HM; soil samples were taken one day after poultry litter was removed from the site.

Chart Graph Placeholder

Table 43. Concentration of Mehlich 3-K in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site LS.

Chart Graph Placeholder

150 days in 2007 on three Delaware farms; soil samples were taken 1 day after poultry litter was removed from each site (sites had no treatments).

Chart Graph Placeholder

Table 45. Concentration of Mehlich 3-K in the soil after poultry litter  was piled for 15 to 180 days in 2006 as Site TR1; soil samples were taken the same day the poultry litter was removed.

Chart Graph Placeholder

Table 46. Concentration of Mehlich 3-K in the soil after poultry litter was piled for 15 to 180 days in 2007 at Site TR2; soil samples were taken the same day the poultry litter was removed.

Chart Graph Placeholder

Table 47. Concentration of soluble salts in the soil after poultry litter was piled for 150 days in 2006 at Site CB; soil samples were taken 1 day after poultry litter was removed from the site.

Chart Graph Placeholder

Table 48. Concentration of soluble salts in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site GT.

Chart Graph Placeholder

Table 49. Concentration of soluble salts in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site HM.

Chart Graph Placeholder

Table 50. Concentration of soluble salts in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site LS.

Chart Graph Placeholder

Table 51. Concentration of soluble salts in the soil after poultry litter was piled for 150 days in 2007 on three Delaware farms; soil samples were taken 1 day after poultry litter was removed from each site (sites had no treatments).

Chart Graph Placeholder

Table 52. Concentration of soluble salts in the soil after poultry litter was piled for 15 to 180 days in 2006 at Site TR1; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 53. Concentration of soluble salts in the soil after poultry litter was piled for 15 to 180 days in 2007 at Site TR2; soil samples were taken the same day the poultry litter was removed.

Chart Graph Placeholder

Chart Graph Placeholder

Figure 8. Relationships between concentrations of soluble salts and soil potassium and soil sulfur in the surface six-inch soil layer during the first two years of this study.

Chart Graph Placeholder

Figure 9. Relationships between concentrations of soluble salts and soil ammonium and soil nitrate in the surface six-inch soil layer during the first two years of this study.

Table 54. Concentration of sulfur in the soil after poultry litter was piled for 150 days in 2006 at Site CB; soil samples were taken 51 days after poultry litter was removed from the site.

Chart Graph Placeholder

Table 55. Concentration of sulfur in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site GT.

Chart Graph Placeholder

Table 56. Concentration of sulfur in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site HM.

Chart Graph Placeholder

Table 57. Concentration of sulfur in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site LS.

Chart Graph Placeholder

Table 58. Concentration of sulfur in the soil after poultry litter was piled for 150 days in 2007 on three Delaware farms; soil samples were taken 1 day after poultry litter was removed from each site (sites had no treatments).

Chart Graph Placeholder

Table 59. Concentration of sulfur in the soil after poultry litter was piled for 15 to 180 days in 2006 at Site TR1; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 60. Concentration of sulfur in the soil after poultry litter was piled for 15 to 180 days in 2007 at Site TR2; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 61. Concentration of calcium in the soil after poultry litter was piled for 150 days in 2006 at Site CB; soil samples were taken 51 days after poultry litter was removed from the site.

Chart Graph Placeholder

Table 62. Concentration of calcium in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site GT.

Chart Graph Placeholder

Table 63. Concentration of calcium in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site HM.

Chart Graph Placeholder

Table 64. Concentration of calcium in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site LS.

Chart Graph Placeholder

Table 65. Concentration of calcium in the soil after poultry litter was piled for 150 days in 2007 on three Delaware farms; soil samples were taken 1 day after poultry litter was removed from each site (sites had no treatments).

Chart Graph Placeholder

Table 66. Concentration of calcium in the soil after poultry litter was piled for 15 to 180 days in 2006 at Site TR1; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 67. Concentration of calcium in the soil after poultry litter was piled for 15 to 180 days in 2007 at Site TR2; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 68. Concentration of magnesium in the soil after poultry litter was piled for 150 days in 2006 at Site CB; soil samples were taken 1 day after poultry litter was removed from the site.

Chart Graph Placeholder

Table 69. Concentration of magnesium in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site GT.

Chart Graph Placeholder

Table 70. Concentration of magnesium in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site HM.

Chart Graph Placeholder

Table 71. Concentration of magnesium in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site LS.

Chart Graph Placeholder

Table 72. Concentration of magnesium in the soil after poultry litter was piled for 150 days in 2007 on three Delaware farms; soil samples were taken 1 day after poultry litter was removed from each site (sites had no treatments).

Chart Graph Placeholder

Table 73. Concentration of magnesium in the soil after poultry litter was piled for 15 to 180 days in 2006 at Site TR1; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 74. Concentration of magnesium in the soil after poultry litter was piled for 15 to 180 days in 2007 at Site TR2; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 75. Concentration of copper in the soil after poultry litter was piled for 150 days in 2006 at Site CB; soil samples were taken 1 day after poultry litter was removed from the site.

Chart Graph Placeholder

Table 76. Concentration of copper in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site GT.

Chart Graph Placeholder

Table 77. Concentration of copper in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site HM.

Chart Graph Placeholder

Table 78. Concentration of copper in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site LS.

Chart Graph Placeholder

Table 79. Concentration of copper in the soil after poultry litter was piled for 150 days in 2007 on three Delaware farms; soil samples were taken 1 day after poultry litter was removed from each site (sites had no treatments).

Chart Graph Placeholder

Table 80. Concentration of copper in the soil after poultry litter was piled for 15 to 180 days in 2006 at Site TR1; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 81. Concentration of copper in the soil after poultry litter was piled for 15 to 180 days in 2007 at Site TR2; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 82. Concentration of manganese in the soil after poultry litter was piled for 150 days in 2006 at Site CB; soil samples were taken 1 day after poultry litter was removed from the site.

Chart Graph Placeholder

Table 83. Concentration of manganese in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site GT.

Chart Graph Placeholder

Table 84. Concentration of manganese in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site HM.

Chart Graph Placeholder

Table 85. Concentration of manganese in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site LS.

Chart Graph Placeholder

Table 86. Concentration of manganese in the soil after poultry litter was piled for 150 days in 2007 on three Delaware farms; soil samples were taken 1 day after poultry litter was removed from each site (sites had no treatments).

Chart Graph Placeholder

Table 87. Concentration of manganese in the soil after poultry litter was piled for 15 to 180 days in 2006 at Site TR1; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 88. Concentration of manganese in the soil after poultry litter was piled for 15 to 180 days in 2007 at Site TR2; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 89. Concentration of zinc in the soil after poultry litter was piled for 150 days in 2006 at Site CB; soil samples were taken 1 day after poultry litter was removed from the site.

Chart Graph Placeholder

Table 90. Concentration of zinc in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site GT.

Chart Graph Placeholder

Table 91. Concentration of zinc in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site HM.

Chart Graph Placeholder

Table 92. Concentration of zinc in the soil after poultry litter was piled for 150 days in 2007 on a Delaware farm; soil samples were taken 1 day after poultry litter was removed from Site LS.

Chart Graph Placeholder

Table 93. Concentration of zinc in the soil after poultry litter was piled for 150 days in 2007 on three Delaware farms; soil samples were taken 1 day after poultry litter was removed from each site (sites had no treatments).

Chart Graph Placeholder

Table 94. Concentration of zinc in the soil after poultry litter was piled for 15 to 180 days in 2006 at Site TR1; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Table 95. Concentration of zinc in the soil after poultry litter was piled for 15 to 180 days in 2007 at Site TR2; soil samples were taken the same day poultry litter was removed.

Chart Graph Placeholder

Complete the form below to download this document now.

https://bit.ly/2Wmp2Of