Soilworks products are the industry’s top standard due to our insistence on creating high performance soil stabilization and dust control products that stand up to rigorous testing – both in the lab and in the field. Our commitment to quality and performance has led to our involvement and testing in hundreds of real-world situations. The following library of reports, presentations, specifications, approvals and other similar documents provide you, our customer, the transparency and dependable assurance that is expected from Soilworks.
The Sheldon Mine Tailings Pile Remediation Project, managed by the U.S. Environmental Protection Agency (EPA) Region 9, focused on dust control, erosion mitigation, and soil stabilization to prevent the migration of arsenic, lead, and other toxic heavy metals. The existing tailings cap had failed, leading to fugitive dust emissions and acid mine drainage (AMD) contamination in Lynx Creek and surrounding groundwater. The EPA’s mitigation plan incorporated Gorilla-Snot, a biodegradable synthetic copolymer, to stabilize disturbed soils and prevent airborne dust migration during remediation efforts.
Additional site stabilization efforts included grading, hydroseeding, and the application of vegetative cap systems to create a long-term protective barrier. The EPA’s implementation of Gorilla-Snot for dust suppression ensured safe air quality levels, reduced contaminated soil dispersion, and supported environmental compliance with state and federal standards. Contact Soilworks for specialized dust control and soil stabilization solutions for mine tailings remediation, environmental restoration, and hazardous site containment.
Sheldon Mine Tailings Pile Cap & Drainage Enhancements
March 6, 2013
Dan Shane, US EPA R9 FOSC
Grace Ma, US EPA CIC
Brian Milton, START Contractor
Outline
Overview-
Why are we here?
Overview-
What will the EPA do about it?
Overview-
What are the impacts to local residents?
Overview-
What will the EPA do to mitigate these impacts?
Gorilla-Snot – non-toxic glue
Traffic Control and Road Crossings
Traffic Control Plan
Vicinity Map


Background
Tailings Pile


Why is there a Problem?
Remedial Actions
Site Drainage Improvements
Evapotranspiration Covers-
How do they work?
The Vegetative Cap

Erosion Control
Import Quantities

Project Summary
Eagle Road Crossing (plan view)

Eagle Road Crossing (section)

Walker Road Crossing (plan view)

Walker Road Crossing (section)

French Drain System

Tailings Pile Grading Plan

A Few Definitions