Soilworks products are the industry’s top standard due to our insistence on creating high performance soil stabilization and dust control products that stand up to rigorous testing – both in the lab and in the field. Our commitment to quality and performance has led to our involvement and testing in hundreds of real-world situations. The following library of reports, presentations, specifications, approvals and other similar documents provide you, our customer, the transparency and dependable assurance that is expected from Soilworks.
The Tranque Los Quillayes dam site successfully applied Soiltac to mitigate dust emissions in the buffer zone, covering 70 hectares between November 2017 and January 2018. This dust suppression initiative aimed to reduce particulate matter suspended by strong winds, improving air quality and environmental safety in the surrounding area. Soiltac was applied across six different areas, forming a durable, water-resistant crust that effectively controlled dust migration and stabilized loose soil.
For dam site stabilization, large-scale dust suppression, and regulatory compliance, Soiltac provides a proven, field-tested solution. Contact Soilworks for technical specifications and application strategies.
COLLABORATIVE WORK SPACES OF CUNCUMEN
Successfully complete product application to mitigate dust in the buffer zone
ADVISORS 2018
January 7, 2018 Quillayes Table | Closure of the Tranque, News

With the aim of continuing to reduce the pa1ticulate matter in suspension that is occasionally generated by strong winds in the area of Tranque Los Quillayes, between November 2017 and January 2018 a reactive product called Soiltac was applied in six different areas of this zone, covering an area of 70 hectares.

In yellow the areas of Tranque Los Quil/ayes in which Soi/tac was applied