Soilworks products are the industry’s top standard due to our insistence on creating high performance soil stabilization and dust control products that stand up to rigorous testing – both in the lab and in the field. Our commitment to quality and performance has led to our involvement and testing in hundreds of real-world situations. The following library of reports, presentations, specifications, approvals and other similar documents provide you, our customer, the transparency and dependable assurance that is expected from Soilworks.

Yodaville Training Complex – Subcontractor Daily Report (TPD2209018)

Project: Yodaville Training Complex

Subcontract No. S.302026.0.DTS.22, TO 002

Location: MCAS YUMA, AZ

Prepared by: G.Hart

Thursday, 9/22/22

SUBCONTRACTOR DAILY REPORT

 

Weather: Sunny                           Temperatures: Low 82°F High 101°F                                            Winds: W 5-12 mph

 

PRESENT ON SITE:

Personnel Title Employer Hours
George Hart Project Manager DTS 10
Jessica Dial UXO Tech II/Admin DTS 10
Anthony Dial UXO Tech III DTS 10
Raul Martinez UXO Tech III DTS 10
Damian Bourdukofsky UXO Tech II DTS 10
Travis Hollowell UXO Tech II DTS 10
Robert Brooks Heavy Equipment Operator DTS 10
Daniel Guerrero UXO Tech I DTS 10
 

 

JOB SAFETY

WAS A JOB SAFETY MEETING HELD THIS DATE? (If YES attach

copy of the meeting minutes)

YES NO Total Work Hours on Job Site this Date 80
WERE THERE ANY LOST TIME ACCIDENTS THIS DATE? (If

YES attach copy of completed OSHA report)

 

YES

 

NO

Cumulative Total of Work Hours From Previous Report  

690

 

WAS HAZARDOUS MATERIAL/WASTE RELEASED INTO THE

ENVIRONMENT? (If YES attach description of incident and proposed action.)

 

YES

 

NO

 

Total Work Hours from Start of Project

 

770

 

EQUIPMENT ON SITE:

Equipment Quantity Equipment Quantity
Pickup Truck 4wd 4 Bobcat 870 1
Support Trailer 1 Peterbilt Trucks 2
5 ton Dump Truck 1 Flatbed/Low Boy Trailers 2
1 Polaris Rangers 1 CAT 938 Loader 1
1 Cutting Trailers 1 Cutting Gases Oxygen 1
CASE Loader at Aux2 1 Cutting Gases Propane 1

 

DAILY PRODUCTION:

 

  • Arrived at 0630 hrs at Range Performed a tailgate safety brief with BSE.
  • 0645 BSE and DTS departed
  • BSE brings 1 40’ CCT, we painted, cut windows and placed the one
  • Applied 2nd coat of soil stabilizer to soccer field,
  • Started placing Soiltac on interior Yodaville
  • Grader arrives at 1130, started grading the MLT track at 1245
  • Filled craters and repaired damaged roads on MLT track
  • Filled water truck at County 17 canal
  • 1615 Departed for the

 

 

 

Activity Total to Complete Daily Complete Total Complete Percent Complete
CCTs Replaced 46 1 43 93%
Vehicle Targets Removed 13 13 13 100%
Soil Tackifier Applied Soccer Field (Green) N/A 100% 100% 100%
Soil Tackifier Applied MLT (Black) N/A 15% 15% 15%
MLT Track Repaired N/A 100% 100% 100%
CCT Transported to AUX II 46 7 46 100%
Process and Recycle CCT’s 46 0 0 0%

 

 

 

 

General Notes/Comments

  • We are caught up with painting and cutting windows on the CCT’s currently Waiting for delivery for 3 more 40’ containers. Should be getting 3 tomorrow.
  • 2 out of 12 work days remain, Saturday will be last work day at Then move to Process and Recycling at AUX 2.
  • Received temporary water permit from Yuma Irrigation District to fill water truck, water point at range is down due to powerlines.
  • Travis and Rob arrive with two trucks and Subcontract at 1 North with ERRG is complete.
  • Used all 125 gallons of desert tan Tapped into older excess paint from BSE about 10 gallons.

 

 

Shipping Summary:

  • None

 

Unexploded Ordnance Found:

  • None

 

Site Visitors:

  • No Visitors

 

 

 

Loading Soiltac® into Truck

2nd Coat on Soccer Field

Grading MLT Track

Applying Soiltac to Interior Yodaville Roads